煤矿充填工作面支巷围岩变形破坏规律研究

Deformation and failure laws of surrounding rock in branch roadways of backfill mining faces in coal mines

  • 摘要:
    目的 为探究充填开采时工作面支巷围岩变形破坏时空演化规律,以潞安集团的潞安矿区某矿1#充填工作面为背景,
    方法 通过FLAC3D数值软件建立包含充填开采工作面及周边围岩的数值模型,模拟顺槽、支巷开采、拉底以及充填过程,结合现场位移监测掌握充填开采支巷服务各阶段变形特点与变形量,进而研究支巷开采过程中的围岩变形破坏规律。
    结果及结论 结果表明,顺槽开采后围岩最大竖向位移32.2 mm,水平位移70.2 mm,塑性区破坏深度顶板1.5 m、底板4.0 m、两帮2.0 m;支巷拉底前期对两帮围岩收敛变形影响显著。第1轮支巷开采后最大竖向位移95.0 mm,水平位移83.0 mm,塑性区破坏深度顶板2.0 m、底板2.0 m、两帮5.0 m;第2轮22#支巷拉底过程中,前80 m拉底对两帮围岩收敛变形影响最大,拉底完成后两帮围岩最大收敛变形量100.9 mm;现场监测中,随着拉底进度增加,支巷围岩变形会相对集中在支巷20~90 m位置,最大变形量达90 mm,与数值模拟结果高度吻合。

     

    Abstract: To explore the spatiotemporal evolution law of surrounding rock deformation and failure in the branch roadway of a working face during backfill mining, this paper takes the 1# backfill working face of a certain mine in Lu'an mining area of Lu'an Group as the research background. A numerical model including the backfill mining working face and its surrounding rock was established using FLAC3D software to simulate the processes of gateway and branch roadway mining, floor pulling, and backfilling. Combined with on-site displacement monitoring, the deformation characteristics and deformation amounts of the branch roadway during each service stage of backfill mining were analyzed, and further research was conducted on the law of surrounding rock deformation and failure during the branch roadway mining process. The results show that after the gateway excavation, the maximum vertical displacement of the surrounding rock in the roadway is 32.2 mm, and the horizontal displacement is 70.2 mm. The plastic zone failure depth reaches 1.5 m in the roof, 4.0 m in the floor, and 2.0 m in the two sides. The early stage of floor pulling in the branch roadway has a significant impact on the convergence deformation of the surrounding rock on both sides. After the first round of branch roadway mining, the maximum vertical displacement is 95.0 mm, and the horizontal displacement is 83.0 mm; the plastic zone failure depth is 2.0 m in the roof, 2.0 m in the floor, and 5.0 m in the two sides. During the floor pulling process of the 22# branch roadway in the second round, the first 80 meters of floor pulling have the greatest impact on the convergence deformation of the surrounding rock on both sides, and the maximum convergence deformation of the surrounding rock on both sides after floor pulling is 100.9 mm. In on-site monitoring, as the floor pulling progresses, the deformation of the surrounding rock in the branch roadway is relatively concentrated in the 20~90 m section of the branch roadway, with the maximum deformation amount reaching 90 mm, which is consistent with the numerical simulation results.

     

/

返回文章
返回